  • Imprecise earned duration model for time evaluation of construction projects with risk considerations Imprecise earned duration model for time evaluation of construction projects with risk considerations
    Imprecise earned duration model for time evaluation of construction projects with risk considerations

    سال انتشار:

    2020


    عنوان انگلیسی مقاله:

    Imprecise earned duration model for time evaluation of construction projects with risk considerations


    ترجمه فارسی عنوان مقاله:

    مدل مدت زمان به دست امده برای ارزیابی زمان پروژه های ساختمانی با ملاحظات ریسکی


    منبع:

    Sciencedirect - Elsevier - Automation in Construction, 111 (2020) 102993: doi:10:1016/j:autcon:2019:102993


    نویسنده:

    Amir Mohammad Hamzeha, Seyed Meysam Mousavia,⁎, Hossein Gitinavardb


    چکیده انگلیسی:

    Monitoring and estimating the time performance of projects are two crucial factors which lead the companies to be prosperous. To address the issue, the most recent time-based method is earned duration management (EDM) which is used as an efficient technique. This research presents a new triangular intuitionistic fuzzy-EDM model to improve the applicability of time performance indices and to forecast under uncertain conditions. Since traditional fuzzy sets using membership degrees cannot deal with imprecise quantities in real cases, triangular intuitionistic fuzzy numbers (TIFNs) solve this issue by non-membership and hesitation degrees. In this sake, a TIFN as a special type of intuitionistic fuzzy sets (IFSs), defined on the set of real numbers, shows high capability of modeling ill-known and imprecise information in continuous domains. Besides, the importance of risks in time estimation of EDM is less considered in the literature. In this research, a new time-based risk performance indicator (TBRPI) is developed based on novel risk performance metrics (RPMs) to improve the project time performance estimating of EDM. In this respect, the significance of each RPM could increase the accuracy of the proposed approach, in which a new triangular intuitionistic fuzzy group decision method is presented for obtaining the RPMs and constituent factors (CFs)’ weights. Finally, a real case study about seawater intake basin construction project is provided to represent the applicability and feasibility of the proposed triangular intuitionistic fuzzy risk-based EDM model.
    Keywords: Earned duration management | Construction projects | Risk performance indicator | Triangular intuitionistic fuzzy sets | Uncertainty


    سطح: متوسط
    تعداد صفحات فایل pdf انگلیسی: 14
    حجم فایل: 2350 کیلوبایت

    قیمت: رایگان


    توضیحات اضافی:




اگر این مقاله را پسندیدید آن را در شبکه های اجتماعی به اشتراک بگذارید (برای به اشتراک گذاری بر روی ایکن های زیر کلیک کنید)

تعداد نظرات : 0

الزامی
الزامی
الزامی
rss مقالات ترجمه شده rss مقالات انگلیسی rss کتاب های انگلیسی rss مقالات آموزشی
logo-samandehi